Progress Report.


DT: 31 October 2001

Construction of new houses is going on at seven different places and 50% of the houses atleast will be completed by this year end.
SNO.VILLAGENO. OF HOUSES
1Mithapasvaria153
2Devgadh211
3Jivapar208
4Hamiramora23
5Jakhotra267
6Mayapur81
7Chapredi295
Three new sites have been innaugurated in Vallaphpur for 140 houses. Survey and Ploting has began.

Position of Infrastructure facilities in Villages.

Gram Mandir has been completed in Mithapasvaria and work is in progress in Devgadh, Mayapur, Hamiramora and Jakhotra.
Panchayat Ghar is being constructed in six villages i.e. Mithapasvaria, Devgadh, Mayapur, Jivapar, Hamiramora and Jakhotra. The work is still in progress.

Schools

Number of new schools are being built in six districts. They are: 4 in Banaskantha; 9 in Surendranagar; 14 in Jamnagar; 4 in Rajkot; 21 in Kutch and 8 in Patan. Construction of 4 schools have been completed i.e. one in Banaskantha, two in Kutch and one in Patan. Construction work of rest of the schools will hopefully be completed by the 15th of November 2001.

DT: 31 August 2001

Kutch which has as average rainfall of only 7" received 17" in August, which has hampered the ongoing rehabilitation work. The construction of at least 35 houses will be completed by the end of September. Hamiramora site with 23 houses is scheduled for completion at the end of October.

The exising plants of construction materials have been sifted close to work sites so hopefully the work pace will accelerate from October onwards.

Many of the schools are being constructed at the same location. The removal of debris, uprooting foundation, demolition of partial structure etc., have comparatively taken longer time.

Activity Report: Three new sites were inaugurated at Vallabhpur for 140 houses, Vachhrajpur for 57 and Visnagar for 204 houses. Gram Mandir is in progress in Mayapur and Hamiramora. Construction of Panchayat Ghar is in progress in Mithapasvaria and Mayapur.

Work has started for construction of 44 schools. Details as below:

District Work Started for Construction of Schools


Banaskantha2
Surendranagar7
Jamnagar9
Rajkot5
Kutch18
Patan3


Total44

DT: 20 August 2001

Work is in progress in 6 villages. They are Mitha Pasvaria, Devgarh, Mayapur, Jivapar, Chapredi and Jakhotra.

The number of houses taken up in each village are as follows:

1. Mitha Pasvaria157
2. Devgarh222
3. Mayapur135
4. Jivapar202
5. Chapredi295
6. Jakhotra